Boiler barrel painted, cab receives its first coat of paint
The lagged and re-clad boiler barrel has now been primed and painted, the overhauled fittings and pipes have been refitted to the boiler barrel, and the pipes have been lagged:




In the sleeping coach, the new batteries were placed in the battery box, the 24 V charging system was tested and commissioned, and the overhauled axle generator was fitted and connected. The final work on the brake overhaul has been completed, and our sleeping coach now also has a 10 bar line:


The cab has now also been given a first coat of paint, both inside and out:


Back in March this year, the mechanical part of the brake still remaining on the loco was removed. In a concentrated effort, the connecting and coupling rods were taken off, the brake parts removed and the rods then refitted. The piston rods were also removed.
So the loco is once again seen with her rods, but without brake rigging. Only the middle connecting rod was removed for the transfer to the works:



On the sleeping coach, the battery box was repaired and fitted with new timber. The new batteries can now be installed.