Smokebox finished, tender wheelsets painted

Eisenbahnwerkstätten Krefeld (EWK) has finished the smokebox, and we were able to carry out the accompanying work, such as fitting the boiler cladding on the first boiler ring. The sheet-metal work also continues on the boiler barrel and the rear boiler section, where we keep having to repair small sheets, sometimes make new ones, and the fitting itself remains very laborious:

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted

In addition, the tender wheelsets have been inspected after sandblasting and then painted by us. They are already at the specialist workshop, which will re-tyre them over the coming weeks:

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted

Otherwise, our hard-working team on site continues to push ahead with completing the boiler fittings. Working parties take place for this almost every Saturday and sometimes during the week as well:

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted

Smokebox finished, tender wheelsets painted