Boiler lagging and cladding sheets being fitted
After the successful hydraulic test in November, our working parties in January were dominated by fitting the remaining boiler lagging and boiler cladding sheets:







Fitting the boiler cladding sheets is not only a sign that a lot of the work on the boiler is finished; it is also a milestone that has to be reached before all the other fitting work can go ahead. What follows now, and is being prepared intensively behind the scenes, includes for example making a new cab floor to the original drawing, and fitting the footplate equipment such as the reversing stand, brake valves and brake pipes, and so on and so on...






A jump back in time of about 8 years:

At Eisenbahnwerkstätten Krefeld (EWK) the smokebox is almost finished. The plate sections, laboriously fitted to a complex mathematical intersection shape, have been fully welded. Now the brackets for the smokebox baffle plates are being welded to the new smokebox plate, and the fitted-bolt holes in the smokebox saddle are being reamed through:




We are delighted by the excellent and sometimes even large turnout at the working parties; the "hard core" is on site almost every Saturday. Time and again there are also "newcomers" among the active members, and so we hope that even more people will join the working parties. They take place almost every week... so if you have the time and feel like it, just get in touch. Many thanks for the great support!