Tender interior coated, new superheater elements under way

We have now fully coated the inside of the tender water tank, and the second coat is under way. The work by Eisenbahnwerkstätten Krefeld (EWK) here is well advanced and has shown real steel fabrication skill. EWK's next jobs are the bogie and the wheelsets.

Tender interior coated, new superheater elements under way

Tender interior coated, new superheater elements under way

Tender interior coated, new superheater elements under way

On the boiler, the inner firebox, the rear boiler section and the boiler barrel are finished, and the front tube plate is now being welded in.

Tender interior coated, new superheater elements under way

EWK has started manufacturing the new superheater elements, and this work is already well advanced:

Tender interior coated, new superheater elements under way

Tender interior coated, new superheater elements under way

Finished are the new blastpipe stand and blastpipe, cast to the original drawing, and the welded feed pipe that carries part of the exhaust steam from the blastpipe stand and blastpipe to the mixing feedwater heater:

Tender interior coated, new superheater elements under way

Tender interior coated, new superheater elements under way