Frame work completed, regulator removed
In Krefeld, Eisenbahnwerkstätten Krefeld (EWK) have completed the decisive steps on the frames. The last fitted bolts have now also been made and will be fitted shortly.

The front firebox support has been removed and will be renewed. The mating surfaces on the frames have already been machined.

We prepared the removal of both tube plates. All the welds were needle-gunned once more and then ground off so that the tube plates can be burnt out. Now it is EWK's turn. One of the key components, the regulator, has been removed together with its regulator rodding and sent for overhaul.

The spotlessly clean cylinders and motion have been painted with zinc dust paint.

The pump bracket has now also received its first coat of primer and is waiting for its paint. Under the drag box, parts that carry the horn stays have been painted RED.


Work was also carried out in Crailsheim. Here the second end wall of the Gbs was completely renewed, so the wagon body is almost finished as far as wood and steel are concerned. That means around 70m² of wooden panels and 500 bolts have been renewed. Next up here is work on the roof and floor, as well as the running gear inspection.