Frames examined for cracks, left-hand cylinder bored out
On behalf of Eisenbahnwerkstätten Krefeld (EWK), an inspector examined the loco's entire frames for damage and cracks. Based on the results, EWK can now really get going on repairing the cracks that were found. On the C axle, the slide plates (machined parts) at the frame horn gap must be renewed, as must the bearer for the front firebox support. As an association, this once again confronts us with a new financial hurdle.

The left-hand cylinder has been bored out by EWK:

The leading bogie has now been cleaned. EWK have already started repairing the individual areas of damage:

Sometimes you think there can't be any spots left on the loco that still bear traces of her working life in days gone by. And then your eye falls on yet more areas that still need cleaning.

In Crailsheim, work on the oil tank continued in parallel. The area around the oil flaps is now finally close to its final clean. In addition, further rusted-through areas were welded. Our Gbs-uv 254 has been put into use as a temporary mess room.