We made good use of the relatively mild winter to continue working on 01 1104.
As an important step towards the boiler overhaul, the remaining tubes have now been removed, which makes for a rather unusual sight inside the boiler.

The inside of the boiler has been thoroughly cleaned and, as the next step, will be inspected once more by the boiler inspector.

The new set of tubes has already been obtained and is currently being prepared for fitting.
Work on the tender is also making clear progress. Following our last update, which reported the removal of the oil tank, intensive sheet-metal work on the tender body has now begun.




The overhaul of the many small parts and fittings is also steadily moving forward. By now most of the small parts removed from the boiler have been overhauled and already primed.